A food and beverage layout gets approved twice, by the building department and by the health authority, and the health authority review is the one that comes first. For restaurant, cafe, bar and hospitality operators in Metro Vancouver, that sequence decides how much of the floor plan is genuinely still open to change once drawings are underway.
Here is the approval order behind a food and beverage layout, what each authority expects to see, and what to settle before a tenant improvement goes out to price.
Vancouver Coastal Health states that floor plans must be reviewed and approved before construction begins, covering new premises, renovations, and existing premises being altered to meet current requirements. Fraser Health is equally direct: written approval from an Environmental Health Officer is needed before work starts, and the establishment must then be built in accordance with the approved plans.
What that drawing has to show is, in practice, the layout brief. Fraser Health’s application package, dated August 2019, asks for three copies of scaled floor plans giving every room its purpose and dimensions, plus the position of handwashing, food preparation, dishwashing and utility sinks, range hoods, refrigeration, cooking and hot holding equipment, the hot water tank and its size, janitorial and beverage stations, seating, and both public and staff washrooms. Equipment specifications and a finishing schedule for floors, walls, ceilings and food contact surfaces go in with it, and the food safety and sanitation plans follow at least two weeks before opening.
Applications begin on the Vancouver Coastal Health food service permits page, or with the Environmental Health Officer for the municipality where the premises sit.
What it means: the approved drawing is the document your opening inspection is measured against, so changes made on site afterwards can mean going back for a re-review. Settle the kitchen layout before demolition is booked, not during.
Metro Vancouver’s Food Sector Grease Interceptor Bylaw 365 requires commercial and institutional kitchens to install and maintain a correctly sized interceptor connected to all required fixtures. The bylaw reaches well past full service restaurants: fast food outlets, cafeterias, bars, bakeries, coffee shops, grocery stores, butcher shops and hospital kitchens are all named. Which fixtures drain to the unit is a layout decision, and so is where the unit sits.
The maintenance regime is what makes placement matter. Interceptors must be pumped out by a service provider every 90 days, or sooner once fats, oils, grease and solids pass 25% of the total liquid depth, whichever comes first, with records kept. A unit boxed in behind fixed millwork or sited under a cooking line turns a routine service call into a closure. Enforcement carries weight: re-inspection fees reach $500, and operating without an interceptor draws a minimum fine of $2,000. Requirements and contacts are on the Metro Vancouver grease interceptor page.
What it means: fix the interceptor size, location and connected fixtures while walls are still movable. Clear access for a 90-day pump-out that will not shut the line down is worth more than the floor space it costs.
Seat count is not only a furniture question. The City of Vancouver issues an occupant load permit setting the maximum number of people who can safely use a gathering space such as a restaurant, and it is often required before a provincial liquor licence.
A Food Primary licensee must separately apply to the Liquor and Cannabis Regulation Branch for a structural change when adding, removing or resizing a service area, moving an exterior entrance or exit, removing or expanding a patio, or changing capacity. That application costs $440 and processing runs up to 10 months, which puts it at the front of the programme rather than the end. Cosmetic work, movable furniture, booth seating, stages and dance floors fall outside it.
Patios carry a drawing set of their own. Vancouver’s private patio permit asks for plans showing the seating layout with aisle widths, furniture dimensions, exits and accessible seating, plus interior drawings labelling each washroom. The patio must be wheelchair accessible with at least one table for people with reduced mobility; where alcohol is served it must be outlined by a railing or planters 0.75 to 1 metre high; and a deck more than 600 mm above grade needs drawings sealed by a structural engineer. A summer patio runs April 1 to October 31 on a development permit fee of $477, against $1,360 and up for a year-round patio, which also needs a building permit. Approvals can take several weeks.
What it means: the 10-month liquor timeline is the long pole. If the work touches a service area, an exterior door, a patio or capacity, that application belongs at the start of the programme rather than alongside construction.
Health approvals run through Vancouver Coastal Health or Fraser Health depending on where the premises sit, and occupant load and patio permits are municipal, so the exact process varies across Metro Vancouver. See our locations page for the areas we serve, and our guide from permits to occupancy for how these approvals sit within the wider programme.
Hallmark Projects builds restaurant, cafe, bar and hospitality tenant improvements across Metro Vancouver. We can help you sequence health authority approval ahead of construction, size and site the grease interceptor so it stays serviceable, and get the liquor and patio applications moving before they hold up the schedule.